Harbin, China · Multi-Phase Food Processing Program

CSC supported McCain Foods at its Harbin campus with rolling upgrades and expansions. The program delivered FM (Factory Mutual), UL (Underwriters Laboratories), and FDA (Food and Drug Administration) qualified systems across process production, temperature control, and site infrastructure.

Photos below are a small representative slice from a much larger body of work.

Harbin food processing campus exterior

Project Overview

CSC served as Owner’s Representative and program partner through multiple phases, coordinating contractors and certifying authorities, aligning design and construction with food safety and FM insurance requirements, and keeping delivery on track through challenging weather and site conditions.

Program Value and Scale

  • $7,600,000 Food Processing Plant upgrade.
  • $8,100,000 Wastewater lagoon for the food processing plant.
  • $4,000,000 FM, UL, and FDA qualified process production line.
  • $6,700,000 FM, UL, and FDA qualified temperature-controlled facility.
  • $3,000,000 FM, UL, and FDA qualified food process line.
  • Multi-year engagement with phased turnovers and continuous improvements.

Key Deliverables

  • Process line expansions and upgrades with sanitary detailing and Quality Assurance / Quality Control (QA/QC) oversight.
  • Temperature-controlled rooms and refrigeration systems, cooling tower work, and electrical room tie-ins.
  • Wastewater lagoon construction and associated site civil improvements.
  • Potato storage complexes (Bins 9 through 12) with structure, foundations, and envelopes.

Execution

  • Owner’s Representative services, schedule and cost control, field decision support.
  • FM, UL, and FDA qualification paths integrated into design and turnover.
  • Contractor coordination, site safety, and inspection management through heavy rain seasons.

At a Glance

Location
Harbin, Heilongjiang, China
Engagement
Multi-phase program, phased turnovers
Qualifications
FM, UL, FDA qualified systems
Scopes
Process lines, temperature control, wastewater lagoon, site civil